Question: You are a project manager working on a project. Your sponsor wants to know who a certain work package is assigned to, what control account

You are a project manager working on a project. Your sponsor wants to know who a certain work package is assigned to, what control account to bill it against, and what work is involved. What document do you refer her to?

A. Scope Management Plan B. WBS C. WBS Dictionary D. Scope Statement