Question: You are a project manager working on a project. Your sponsor wants to know who a certain work package is assigned to, what control account
You are a project manager working on a project. Your sponsor wants to know who a certain work package is assigned to, what control account to bill it against, and what work is involved. What document do you refer her to?
A. Scope Management Plan B. WBS C. WBS Dictionary D. Scope Statement
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts