Question: You are managing a construction project that is currently being initiated. You met with the sponsors, and have started to work on identifying stakeholders. Youve
You are managing a construction project that is currently being initiated. You met with the sponsors, and have started to work on identifying stakeholders. You’ve documented several key stakeholders and identified their needs. Before you can finish initiating the project, your company guidelines require that you make a rough order of magnitude estimate of both time and cost, so that the sponsor can allocate the final budget.
What’s the range of a rough order of magnitude (ROM) estimate?
A. -10% to +10%
B. -50% to +50%
C. -50% to +100%
D. -100% to +200%