Question: You are managing a construction project that is currently being initiated. You met with the sponsors, and have started to work on identifying stakeholders. Youve

You are managing a construction project that is currently being initiated. You met with the sponsors, and have started to work on identifying stakeholders. You’ve documented several key stakeholders and identified their needs. Before you can finish initiating the project, your company guidelines require that you make a rough order of magnitude estimate of both time and cost, so that the sponsor can allocate the final budget.

What’s the range of a rough order of magnitude (ROM) estimate?

A. -10% to +10%

B. -50% to +50%

C. -50% to +100%

D. -100% to +200%

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Construction Project Management Questions!