Question: You are working on a construction project. You, your team, and your senior manager all feel that the work is complete. Your stakeholders have communicated

You are working on a construction project. You, your team, and your senior manager all feel that the work is complete. Your stakeholders have communicated their final acceptance of the project. You are now meeting with your team to update the organizational process assets with a record of knowledge gained about the project to help future project managers with their projects. This is BEST described as:

A. Lessons learned B. Project records C. Project management information system (PMIS)
D. Work performance information