Question: You are working on a project that involves multiple vendors. One of the vendors has been difficult to work with and is not very cooperative.

You are working on a project that involves multiple vendors. One of the vendors has been difficult to work with and is not very cooperative. You have received the latest invoice from them for services and disagree with them about the charges they have listed for the change request that was submitted last month. When you called and spoke with your representative at the company, they refused to budge on the charges. You will likely need to use an alternative dispute resolution (ADR) to get to the bottom of this matter. Which tool and technique of the Control Procurements process does this question describe?

A. Payment systems B. Claims administration C. Procurement performance reviews D. Contract change control system

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Construction Project Management Questions!