Question: You have been asked to select between three projects. Project A has a net present value of $54,750 and will take six months to complete.
You have been asked to select between three projects. Project A has a net present value of $54,750 and will take six months to complete. Project B has a net present value of $85,100 and will take two years to complete. Project C has a net present value of $15,000 and a benefitcost ratio of 5:2. Which project should you choose?
A. Project A B. Project B C. Project C D. There is not enough information to decide