Question: Your client has terminated your project before it is complete. Which of the following is true? A. You must stop all work and release the
Your client has terminated your project before it is complete. Which of the following is true?
A. You must stop all work and release the team immediately B. You must work with the team to document the lessons learned C. You must keep the team working on the project to give your senior management time to talk to the client D. You must update the project management plan to reflect this change