Question: Your project has experienced some changes in performance, and some risks have occurred. EAC and BAC now differ as a result. Your project sponsor is
Your project has experienced some changes in performance, and some risks have occurred.
EAC and BAC now differ as a result. Your project sponsor is asking for an estimate of the cost of the project at completion. Which of the following is true?
A. BAC may no longer be reasonable given the changes in performance, so you should use EAC to forecast the cost at completion.
B. EAC may no longer be reasonable given the changes in performance, so you should use BAC to forecast the cost at completion.
C. BAC may no longer be reasonable given the changes in performance, so you should use ETC to forecast the cost at completion.
D. EAC may no longer be reasonable given the changes in performance, so you should use ETC to forecast the cost at completion.