Question: Your project has experienced some changes in performance, and some risks have occurred. EAC and BAC now differ as a result. Your project sponsor is

Your project has experienced some changes in performance, and some risks have occurred.

EAC and BAC now differ as a result. Your project sponsor is asking for an estimate of the cost of the project at completion. Which of the following is true?

A. BAC may no longer be reasonable given the changes in performance, so you should use EAC to forecast the cost at completion.

B. EAC may no longer be reasonable given the changes in performance, so you should use BAC to forecast the cost at completion.

C. BAC may no longer be reasonable given the changes in performance, so you should use ETC to forecast the cost at completion.

D. EAC may no longer be reasonable given the changes in performance, so you should use ETC to forecast the cost at completion.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Construction Project Management Questions!