Question: Your project sponsor has reviewed the initial project schedule you created for the project. She is not happy with the project end date because it

Your project sponsor has reviewed the initial project schedule you created for the project.

She is not happy with the project end date because it doesn’t match the promise date she gave the customer. You decide to use some compression techniques first. Which of the following statements should you keep in mind (and know to be true) regarding duration compression?

A. Crashing is a compression technique that typically produces a viable alternative.

B. Fast-tracking is a compression technique that typically results in increased costs.

C. Schedule compression shortens the project schedule but doesn’t change the project scope.

D. Crashing is a compression technique that typically results in increased risk.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Construction Project Management Questions!