Question: Youre managing a software project. Your team has discovered a problem, and as a result youve requested a change. The change will cost the project
You’re managing a software project. Your team has discovered a problem, and as a result you’ve requested a change. The change will cost the project an extra three weeks, but without it several stakeholders might have problems with the final product. What’s the NEXT thing that you should do?
A. Instruct the team to make the change B. Call a meeting with each stakeholder to figure out whether or not to make the change C. Document the change and its impact, and put it through the change control system D. Don’t make the change because it will delay the project