Question: As the project progresses from initiation through planning and executing, and additional detail is gathered, the range of values for the project cost estimate will:
As the project progresses from initiation through planning and executing, and additional detail is gathered, the range of values for the project cost estimate will:
a. broaden
b. stay the same
c. narrow
d. be replaced with a single number
Step by Step Solution
3.39 Rating (161 Votes )
There are 3 Steps involved in it
The correct answer is c narrow As a project progresses fr... View full answer