When the demand for resources is greater than the available supply, the project manager can use a

Question:

When the demand for resources is greater than the available supply, the project manager can use a scheduling method that adjusts the start and finish dates of activities to address resource limits or constraints. This technique is called _____________.

a. fast tracking

b. crashing

c. resource leveling

d. critical path method

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Contemporary Project Management

ISBN: 9780357715734

5th Edition

Authors: Timothy Kloppenborg, Vittal S. Anantatmula, Kathryn Wells

Question Posted: