Kapoor Engineering Company undertakes a long-term contract which involves the fabrication of prestressed concrete blocks and the erection of the

Question:

Kapoor Engineering Company undertakes a long-term contract which involves the fabrication of prestressed concrete blocks and the erection of the same on consumer's site. 

The following is supplied regarding the contract which is incomplete on 31st March, 2001. Cost incurred:

You are required to prepare a statement for submission to the management indicating:

(a). The estimated profit on the completion of the contract,

(b). The estimated profit to date on the contract. 

This problem has been solved!


Do you need an answer to a question different from the above? Ask your question!

Step by Step Answer:

Related Book For  answer-question

Cost Accounting

ISBN: 9780070221628

4th Edition

Authors: Jawahar Lal, Seema Srivastava

Question Details
Chapter # 10- Job-Order Costing: Cost Flows and External Reporting
Section: Problem
Problem: 13
View Solution
Create a free account to access the answer
Cannot find your solution?
Post a FREE question now and get an answer within minutes. * Average response time.
Question Posted: September 05, 2023 06:19:09