Use of iearning curve tabies The S & J Engineering Company utilized 1,200 hours of labor to
Question:
Use of iearning curve tabies The S & J Engineering Company utilized 1,200 hours of labor to design and write production specification for the production line of a new manufacturing plant the firm has been hired to design. The company must perform the same services for 16 additional production lines.
total cumulative time of completing work on all 17 production lines and also the labor time for the 17th production line design and specification process,
b. Repeat the requirements in part a assuming that design labor for this type of activity is subject to a 93 percent learning curve.