A customers order is delivered (received by the customer) on December 1, 2022. This order was placed

Question:

A customer’s order is delivered (received by the customer) on December 1, 2022. This order was placed with the company on September 1, 2022, and received by the manufacturing department on September 15, 2022. Actual production on the order began on October 15, 2022, and was completed November 15, 2022. Based on this information, calculate the following for this order: 

(a) Total customerresponse time (CRT), 

(b) Order receipt time, 

(c) Manufacturing lead (cycle) time, 

(d) Manufacturing wait time, 

(e) Manufacturing (processing) time, 

(f) Delivery time.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Financial Accounting

ISBN: 9781260006452

17th Edition

Authors: Jan Williams, Susan Haka

Question Posted: