Question: On average, the manufacturing (processing) time spent per order is approximately 4 days. In addition, a typical order spends 4 days moving from process to

On average, the manufacturing (processing) time spent per order is approximately 4 days. In addition, a typical order spends 4 days moving from process to process, 3 days in storage, and 2 days in inspection. For an average order, what is the manufacturing cycle efficiency (%), rounded to 1 decimal place (e.g., 32.463% = 32.5%)?

Step by Step Solution

3.46 Rating (162 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Manufacturing cycle efficiency MCE is defined as the ratio of valueadded time to the su... View full answer