Question: On average, the manufacturing (processing) time spent per order is approximately four days. In addition, a typical order spends four days moving from process to

On average, the manufacturing (processing) time spent per order is approximately four days. In addition, a typical order spends four days moving from process to process, three days in storage, and two days in inspection. For an average order, what is the manufacturing cycle efficiency?

Step by Step Solution

3.39 Rating (165 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Manufacturing cycle efficiency MCE is defined as the ratio of valueadded time to the sum ... View full answer