Question: Blitz Inc. uses three different substitutable products in the production process. In the last production period, they used a total of 555,000 litres: 138,750 litres

Blitz Inc. uses three different substitutable products in the production process. In the last production period, they used a total of 555,000 litres: 138,750 litres of solution E, 222,000 litres of solution T; and 194,250 litres of solution A. The standard cost card follows:

 Standard Quantity 10 litres Cost $0.50 per litre $0.10 per litre $0.35 per litre Solution E $ 5.00 21 litres Solution T


During this production period, 11,000 batches were produced.


Required:

A. Calculate the materials quantity variance.

B. Calculate the mix and yield variances for each solution.

C. Calculate the total mix and yield variances.

D. Write a memo explaining to management what happened during this production period.

Standard Quantity 10 litres Cost $0.50 per litre $0.10 per litre $0.35 per litre Solution E $ 5.00 21 litres Solution T Solution A $ 2.10 $ 6.65 19 litres $13.75

Step by Step Solution

3.46 Rating (178 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

A B and C Actual Quantity x Standard Price Materials Quantity Variance Standard Quantity Allowed x S... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (2 attachments)

PDF file Icon

1601_606321ef0da7d_688879.pdf

180 KBs PDF File

Word file Icon

1601_606321ef0da7d_688879.docx

120 KBs Word File

Students Have Also Explored These Related Managerial Accounting Questions!