Question: Blitz Inc. uses three different substitutable products in the production process. In the last production period, they used a total of 555,000 litres: 138,750 litres
Blitz Inc. uses three different substitutable products in the production process. In the last production period, they used a total of 555,000 litres: 138,750 litres of solution E, 222,000 litres of solution T; and 194,250 litres of solution A. The standard cost card follows:

During this production period, 11,000 batches were produced.
Required:
A. Calculate the materials quantity variance.
B. Calculate the mix and yield variances for each solution.
C. Calculate the total mix and yield variances.
D. Write a memo explaining to management what happened during this production period.
Standard Quantity 10 litres Cost $0.50 per litre $0.10 per litre $0.35 per litre Solution E $ 5.00 21 litres Solution T Solution A $ 2.10 $ 6.65 19 litres $13.75
Step by Step Solution
3.46 Rating (178 Votes )
There are 3 Steps involved in it
A B and C Actual Quantity x Standard Price Materials Quantity Variance Standard Quantity Allowed x S... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (2 attachments)
1601_606321ef0da7d_688879.pdf
180 KBs PDF File
1601_606321ef0da7d_688879.docx
120 KBs Word File