Question: The AW of the current process to make motion controllers is $62,000 per year. A replacement process under consideration has estimates of P = $64,000,

The AW of the current process to make motion controllers is $–62,000 per year. A replacement process under consideration has estimates of P = $64,000, AOC = $38,000, and n = 3 years. Three engineers have given their opinions about what the salvage value of the new process may be in 3 years as $10,000, $14,500, and $18,000.

(a) Is the decision to replace the process sensitive to the salvage value estimates at a MARR of 15% per year?

(b) If sensitive, what is the lowest salvage value that justifies the replacement process?

Step by Step Solution

3.50 Rating (170 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a AW current 62000 AW 10000 64000AP153 38000 10000AF153 640000437... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Engineering Economy Questions!