Question: Two people developed first-cut cost estimates to construct a new 130,000 square foot building on a university campus. Person A applied a generalpurpose per unit

Two people developed first-cut cost estimates to construct a new 130,000 square foot building on a university campus. Person A applied a generalpurpose per unit cost estimate of $180 per square foot for the estimate. Individual B was more specific: she used the area estimates and per unit cost factors shown below.

(a) What are the cost estimates developed by the two people?

(b) What is the percent increase between the lower and higher cost estimates?

Cost per ft?, $ Type of Usage Area, % 30 Classroom 125 Laboratory 40 185 Offices 30 110 Furnishings-labs 25 150 Furnishi

Cost per ft?, $ Type of Usage Area, % 30 Classroom 125 Laboratory 40 185 Offices 30 110 Furnishings-labs 25 150 Furnishings-all others 75 25

Step by Step Solution

3.48 Rating (165 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a Cost A 130000180 23400000 Cost B b increase 26097500 2340000023... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Engineering Economy Questions!