HydroLift is trying to determine how long it takes for one product to pass through the production

Question:

HydroLift is trying to determine how long it takes for one product to pass through the production process. The following information was gathered regarding how many days the product spent in various production activities:


image


a. Which of these activities are value-added?b. What is HydroLift’s total cycle time?c. Determine HydroLift’s manufacturing efficiency ratio.d. If HydroLift implements a total quality management program and a just-in-time inventory system, which of these activities could likely be eliminated? What would be the change in the company’s manufacturing efficiency ratio?