Question: Task A is depending on Task B. Task C is dependent on Task A. Task D is dependent on Task E. Task F is dependent
Task A is depending on Task B. Task C is dependent on Task A. Task D is dependent on Task E. Task F is dependent on Task E.
Given that all tasks are of equal duration, what is the critical path?
A. E, D, F B. B, C, D C. B, A, C D. E, F, D