Question: You are developing a scope of work for a project that will utilize extensive technical resources. A request has been made to make modifications to

You are developing a scope of work for a project that will utilize extensive technical resources. A request has been made to make modifications to a user input screen.

Who must approve?

A. Project manager B. Development team leader C. Project sponsor D. End users representative