Question: A first-time project manager is advised by an experienced project manager to plan for cost of quality. The first-time project manager is not sure which

A first-time project manager is advised by an experienced project manager to plan for cost of quality. The first-time project manager is not sure which costs are included in the cost of quality. What would your advice be?

Cost of quality only includes cost of nonconformance.

Cost of quality includes cost of conformance and cost of nonconformance.

Cost of quality only includes prevention costs and internal failure costs.

Cost of quality only includes cost of conformance.