Question: A project manager estimated that a project would require 4375 person hours of effort. The project ended up using 6250 person-hours of effort. The difference

A project manager estimated that a project would require 4375 person hours of effort. The project ended up using 6250 person-hours of effort.

The difference between these two figures is a: