Question: A project manager estimated that a project would require 4375 person hours of effort. The project ended up using 6250 person hours of effort. The
A project manager estimated that a project would require 4375 person hours of effort. The project ended up using 6250 person hours of effort. The difference between these two figures is called a:
A. Variance B. Control Limit C. Threshold D. Standard Deviation