Question: A project manager is considering various classification methods to share information among project stakeholders. Which of the following correctly classifies the different methods used? Pull
A project manager is considering various classification methods to share information among project stakeholders. Which of the following correctly classifies the different methods used?
Pull communication—Meetings; Push communication—
Newsletters; Interactive communication—E-learning repository Interactive communication—Meetings; Push communication—Elearning repository; Pull communication—Newsletters Push communication—Meetings; Pull communication—
Newsletters; Interactive communication—E-learning repository Interactive communication—Meetings; Push communication—
Newsletters; Pull communication—E-learning repository