Question: A project manager is looking at various classification methods to share information among project stakeholders. Which of the following correctly classifies the different methods used?
A project manager is looking at various classification methods to share information among project stakeholders. Which of the following correctly classifies the different methods used?
A. Pull communication - Meetings; Push communication - Newsletters; Interactive communication - E-learning repository B. Interactive communication - Meetings; Push communication - E-learning repository; Pull communication - Newsletters C. Push communication - Meetings; Pull communication - Newsletters; Interactive communication - E-learning repository D. Interactive communication - Meetings; Push communication - Newsletters; Pull communication - E-learning repository