Question: A project manager is preparing the WBS for a software project. The WBS includes all the product and project work but excludes the project management

A project manager is preparing the WBS for a software project. The WBS includes all the product and project work but excludes the project management work. From the following choices, choose a statement that correctly describes this situation.

This is incorrect. Include product work and project management as part of the WBS but exclude project work.

This is incorrect. Project work and project management are part of the WBS, but product work is not.

This is incorrect. Include product work, project work, and project management work.

This is correct. Include product and project work as part of the WBS but exclude project management work.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Fraud Examination Questions!