Question: A project manager is preparing the WBS for a software project. The WBS includes all the product and project work but excludes the project management


A project manager is preparing the WBS for a software project. The WBS includes all the product and project work but excludes the project management work. From the following choices, select a statement that correctly describes this situation.

A. This is incorrect. Product work and project management should be included as part of the WBS, but project work should be excluded.

B. This is incorrect. Project work and project management should be part of the WBS but product work should be excluded.

C. This is incorrect. Product work, project work and project management work should all be included in the WBS D. This is correct. Product and project work should be included as part of the WBS, but project management work should be excluded.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related PMP® Exam Practice Test And Study Guide Questions!