Question: A project manager uses the precedence diagramming method (PDM) for constructing a project schedule network and creates a network diagram for the purpose. He decides

A project manager uses the precedence diagramming method (PDM)

for constructing a project schedule network and creates a network diagram for the purpose. He decides to use the most common type of precedence relationship for all activities. Which of the following relationships would he use?

Start-to-finish (SF)

Finish-to-finish (FF)

Start-to-start (SS)

Finish-to-start (FS)