Question: Along with the project communications management plan, work performance reports are vital inputs to the Manage Communications process. Where do these work performance reports come
Along with the project communications management plan, work performance reports are vital inputs to the Manage Communications process. Where do these work performance reports come from?
Project integration management process All monitoring and controlling processes Plan Communications Management processes Organizational process assets