Question: Although it is highly recommended that lessons learned are captured and documented throughout the project lifecycle, lessons learned are finalized during project closure. At this
Although it is highly recommended that lessons learned are captured and documented throughout the project lifecycle, lessons learned are finalized during project closure. At this stage, responses to high-level questions may be gathered and documented. Which of the following is not an appropriate question to ask at this stage?
What were the top significant project successes?
How relevant the historic lessons learned were to this project during execution?
What obstacles or unanticipated circumstances made it difficult to complete the project?
What should have been done differently in this project?