Question: What does it mean if the Earned Value is equal to Actual Cost? Schedule Variance Index is 1 Project is on budget and on schedule
What does it mean if the Earned Value is equal to Actual Cost?
Schedule Variance Index is 1 Project is on budget and on schedule There is no cost variance There is no schedule variance