Question: Anthony is currently managing a bridge construction project. The project is in the execution phase. During the planning phase of the project, Anthony developed a

Anthony is currently managing a bridge construction project. The project is in the execution phase. During the planning phase of the project, Anthony developed a comprehensive stakeholder engagement plan for the project. However, the frequency of plan review has not yet been defined. How often should Anthony review the stakeholder engagement plan?

On a monthly basis The stakeholder engagement plan cannot be reviewed during the execution of the project.

On a weekly basis On a regular basis; Anthony needs to decide the frequency.