Question: Anthony is currently managing a bridge construction project. The project is in the execution phase. During the planning phase of the project, Anthony developed a
Anthony is currently managing a bridge construction project. The project is in the execution phase. During the planning phase of the project, Anthony developed a comprehensive stakeholder engagement plan for the project. However, the frequency of plan review has not yet been defined. How often should Anthony tevicw the stakeholder engagement plan?
A On a monthly basis
The stakeholder engagement plan cannot be reviewed during execution of the project.
On a weekly basis
On a regular basis; Anchony needs to decide the frequency.