Question: . As project manager you need to let your team know how it is doing on the project schedule overall. Of the 3 project phases

. As project manager you need to let your team know how it is doing on the project schedule overall. Of the 3 project phases in progress to date —

planning, testing and design — you calculate planned value and earned value as shown in the above table.

As a whole, your project is roughly:

a) 10% behind schedule

b) 10% ahead of schedule

c) 10% behind schedule and budget

d) 10% ahead of schedule, but over budget