Question: . As project manager you need to let your team know how it is doing on the project schedule overall. Of the 3 project phases
. As project manager you need to let your team know how it is doing on the project schedule overall. Of the 3 project phases in progress to date —
planning, testing and design — you calculate planned value and earned value as shown in the above table.
As a whole, your project is roughly:
a) 10% behind schedule
b) 10% ahead of schedule
c) 10% behind schedule and budget
d) 10% ahead of schedule, but over budget