Question: Please specify the correct answer without explanation, and also please be sure to answer this third time that I sent these questions to this site

Please specify the correct answer without explanation, and also please be sure to answer this third time that I sent these questions to this site and it was incorrectly resolved.Please specify the correct answer withoutPlease specify the correct answer withoutPlease specify the correct answer withoutPlease specify the correct answer without

1-which of the following is an output of performing integrated change control process A- Approved change request B- Change request C-Work performance data D-Work performance reports 2-which of the following is not considered an emerging practice/trend in project integration management? A-Use of automated tools B- Use of visual management tools C- Expanding the project manager's responsibilities D- On-demand Scheduling 3-what is the process group that contains manage project knowledge process? A-Initiating B- Planning C-Executing D-Monitoring and controlling 4-which of the following describes the develop charter process? A- Leading and performing the work defined in the project management plan implementing approved changes to achieve the projects objectives B- Defining, preparing, and coordinating all plan components and consolidating them into an integrated project management plan C- Developing a document that formally authorizes the existence of a project and provides the project manager with authority to apply organizational resources to project activities D-Tracking, reviewing, and reporting overall progress to meet the performance objectives defined in the project management plan 5-which of the following is not a component of the project charter? A- Measurable project objectives and related success criteria B- High-level requirements C- Summary milestone schedule D- Detailed project schedule 6-which of the following tailoring considerations is mostly related to project integration management? A- Lessons learned B- Stability of requirements C- Resource availability D-Iterative Scheduling with a Backlog 7-what is the most appropriate time to conduct the kick-off meeting? A- At the end of initiating and the start of planning B- At the end of planning and the start of executing C- At the end of executing and the start of closing D- Before the start of initiating 8-which of the following is not a component of the project management plan? A- Quality management plan B- Schedule baseline C- Risk register D- Performance measurement baseline 9-Ibrahim is a project manager of an IT project; during the project execution, after defining all requirements and approving all plans, one of the key stakeholders stated verbally that he wants to add more features to the software: what should Ibrahim do? A-Ibrahim should request the stakeholder to submit a change request, and he should also evaluate the impact of this request on the project objectives B- Ibrahim should reject the stakeholder's request C-Ibrahim should directly implement the required feature D-Ibrahim should raise the issue with the project sponsor 10-At the final stages of an IT project, the project manager is working with the project team to create a document that include the summary of any risks or issues encountered on the project and how they were addressed, what is this document? A- Project charter B- Project management plan C- Final report D- Change log 11-who is responsible for approving, or rejecting the submitted change requests? A- Project manager B- Functional manager C-PMO manager D- Change control board or authorized persons 12-which document contains the status of all change requests? A-Change log B- Change management plan C- Configuration management plan D- Issue log 13-during a kick-off meeting of a construction project, one of the key stakeholders stated that the items being discussed are not appropriate to be discussed in a kick-off meeting; which of the following could be those items which are not a purpose of the kick-off meeting? A- Communicate the objectives of the project B- Gain the commitment of the team for the project C- Explain the roles and responsibilities of each stakeholder D- Defining the project scope and creating the work breakdown structure 14-in the execution stage of a construction project, the project manager requested a team member to provide him with a specific work performance data; which of the following could be this work performance data? A- Reserve burn-down charts B- Actual costs incurred C-Trend lines and forecasts D- Earned value graphs 15-aproduct, service, or result, once delivered by the project, may be handed over to a different group or organization that will operate, maintain, and support it throughout its life cycle; in what project management process this could happen? A-Direct and manage project work B- Monitor and control project work C-Close project or phase D- Perform integrated change control 16-change requests could vary according to the included type of action; what is the action that ensures the future performance of the project work is aligned with the project management plan. A- Corrective action B- Preventive action C- Defect repair D- Updates of project management plan 17-in a construction project, and after recording lessons learned and preparing a final report, the project manager is currently working on the release of team resources; in which project management process the team resources are released? A- Monitor and control project work B- Direct and manage project work C-Close project or phase D- Perform integrated change control 18-who is responsible for applying project integration management? A- The project sponsor B- The project management team C. The project manager D- The project team 19-work performance reports are output of which project management process? A- Direct and manage project work B- Monitor and control project work C- Develop project management plan D- Manage project knowledge 20-which of the following is an output of direct and manage project work process? A-Deliverables B- Verified deliverables C- Accepted deliverables D- Project charter 1-which of the following is an output of performing integrated change control process A- Approved change request B- Change request C-Work performance data D-Work performance reports 2-which of the following is not considered an emerging practice/trend in project integration management? A-Use of automated tools B- Use of visual management tools C- Expanding the project manager's responsibilities D- On-demand Scheduling 3-what is the process group that contains manage project knowledge process? A-Initiating B- Planning C-Executing D-Monitoring and controlling 4-which of the following describes the develop charter process? A- Leading and performing the work defined in the project management plan implementing approved changes to achieve the projects objectives B- Defining, preparing, and coordinating all plan components and consolidating them into an integrated project management plan C- Developing a document that formally authorizes the existence of a project and provides the project manager with authority to apply organizational resources to project activities D-Tracking, reviewing, and reporting overall progress to meet the performance objectives defined in the project management plan 5-which of the following is not a component of the project charter? A- Measurable project objectives and related success criteria B- High-level requirements C- Summary milestone schedule D- Detailed project schedule 6-which of the following tailoring considerations is mostly related to project integration management? A- Lessons learned B- Stability of requirements C- Resource availability D-Iterative Scheduling with a Backlog 7-what is the most appropriate time to conduct the kick-off meeting? A- At the end of initiating and the start of planning B- At the end of planning and the start of executing C- At the end of executing and the start of closing D- Before the start of initiating 8-which of the following is not a component of the project management plan? A- Quality management plan B- Schedule baseline C- Risk register D- Performance measurement baseline 9-Ibrahim is a project manager of an IT project; during the project execution, after defining all requirements and approving all plans, one of the key stakeholders stated verbally that he wants to add more features to the software: what should Ibrahim do? A-Ibrahim should request the stakeholder to submit a change request, and he should also evaluate the impact of this request on the project objectives B- Ibrahim should reject the stakeholder's request C-Ibrahim should directly implement the required feature D-Ibrahim should raise the issue with the project sponsor 10-At the final stages of an IT project, the project manager is working with the project team to create a document that include the summary of any risks or issues encountered on the project and how they were addressed, what is this document? A- Project charter B- Project management plan C- Final report D- Change log 11-who is responsible for approving, or rejecting the submitted change requests? A- Project manager B- Functional manager C-PMO manager D- Change control board or authorized persons 12-which document contains the status of all change requests? A-Change log B- Change management plan C- Configuration management plan D- Issue log 13-during a kick-off meeting of a construction project, one of the key stakeholders stated that the items being discussed are not appropriate to be discussed in a kick-off meeting; which of the following could be those items which are not a purpose of the kick-off meeting? A- Communicate the objectives of the project B- Gain the commitment of the team for the project C- Explain the roles and responsibilities of each stakeholder D- Defining the project scope and creating the work breakdown structure 14-in the execution stage of a construction project, the project manager requested a team member to provide him with a specific work performance data; which of the following could be this work performance data? A- Reserve burn-down charts B- Actual costs incurred C-Trend lines and forecasts D- Earned value graphs 15-aproduct, service, or result, once delivered by the project, may be handed over to a different group or organization that will operate, maintain, and support it throughout its life cycle; in what project management process this could happen? A-Direct and manage project work B- Monitor and control project work C-Close project or phase D- Perform integrated change control 16-change requests could vary according to the included type of action; what is the action that ensures the future performance of the project work is aligned with the project management plan. A- Corrective action B- Preventive action C- Defect repair D- Updates of project management plan 17-in a construction project, and after recording lessons learned and preparing a final report, the project manager is currently working on the release of team resources; in which project management process the team resources are released? A- Monitor and control project work B- Direct and manage project work C-Close project or phase D- Perform integrated change control 18-who is responsible for applying project integration management? A- The project sponsor B- The project management team C. The project manager D- The project team 19-work performance reports are output of which project management process? A- Direct and manage project work B- Monitor and control project work C- Develop project management plan D- Manage project knowledge 20-which of the following is an output of direct and manage project work process? A-Deliverables B- Verified deliverables C- Accepted deliverables D- Project charter

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!