Question: . As the project manager, you are scheduling some activities in which there is a delay between the finish of the activity and the start
. As the project manager, you are scheduling some activities in which there is a delay between the finish of the activity and the start of the successor activity.
These dependencies would be reflected in the schedule with a ___________.
a) Finish-to-start relationship
b) Lag
c) Start-to-finish relationship
d) Lead