Question: . As the project manager, you are scheduling some activities in which there is a delay between the finish of the activity and the start

. As the project manager, you are scheduling some activities in which there is a delay between the finish of the activity and the start of the successor activity.

These dependencies would be reflected in the schedule with a ___________.

a) Finish-to-start relationship

b) Lag

c) Start-to-finish relationship

d) Lead