Question: . After the 5th month on her project, a project manager found that the cumulative actual expenditures totaled $120,000. The planned expenditures for this length
. After the 5th month on her project, a project manager found that the cumulative actual expenditures totaled $120,000. The planned expenditures for this length of time were $100,000.
How is the project doing?
a) It is ahead of schedule
b) It is in trouble because of a cost overrun
c) It will finish within the original budget
d) The information is insufficient to make an assessment