Question: For projects where a business analyst collaborates with the project managers in managing the project scope, which of the following task is most likely to

For projects where a business analyst collaborates with the project managers in managing the project scope, which of the following task is most likely to be performed by the business analyst?

Acquire project resources Monitor the change control process Elicit, document, and manage stakeholder requirements Control project costs