Question: If the optimistic estimate for an activity is 15 days and the pessimistic estimate is 25 days, what is the realistic estimate? A. 19 days.

If the optimistic estimate for an activity is 15 days and the pessimistic estimate is 25 days, what is the realistic estimate?

A. 19 days.

B. 20days.

C. 21days.

D. Unknown.