Question: In the program evaluation and review technique (PERT), the most likely scenario is given a weight of 4 as compared to the weight of 1

In the program evaluation and review technique (PERT), the most likely scenario is given a weight of 4 as compared to the weight of 1 for each of the pessimistic and optimistic scenarios.

The pessimistic estimate for an activity is 25 days, the optimistic estimate is 5 days, and the most likely estimate is 10 days. Calculate the expected estimate by using the PERT technique.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Project Management For Small Projects Questions!