Question: In the program evaluation and review technique (PERT), the most likely scenario is given a weight of 4 as compared to the weight of 1
In the program evaluation and review technique (PERT), the most likely scenario is given a weight of 4 as compared to the weight of 1 for each of the pessimistic and optimistic scenarios.
The pessimistic estimate for an activity is 25 days, the optimistic estimate is 5 days, and the most likely estimate is 10 days. Calculate the expected estimate by using the PERT technique.