Question: In a textile manufacturing project, a team divided the project work into 35 work packages and assigned a few work packages to the design department
In a textile manufacturing project, a team divided the project work into 35 work packages and assigned a few work packages to the design department for review. After the review, the manager of the design department requested that the team further divide the work packages into more manageable work components for estimating and scheduling resources. Which of the following techniques should the team use to satisfy the manager's request?
Decomposition The parametric estimating The precedence diagramming method The bottom-up estimating