Question: In predictive projects, the scope baseline for the project is used to analyze a projects scope performance. On the other hand, projects with adaptive lifecycles

In predictive projects, the scope baseline for the project is used to analyze a project’s scope performance. On the other hand, projects with adaptive lifecycles use:

WBS WBS dictionary Scope statement Backlogs