Question: James is currently managing a software upgrade project. He has recently identified and analyzed his key project stakeholders. He is now searching his organizational process

James is currently managing a software upgrade project. He has recently identified and analyzed his key project stakeholders. He is now searching his organizational process assets for a template with which he can update the results of this analysis along with the planned strategies required to engage the stakeholders effectively. Which of the following should he search for?

Risk management plan Change request form Stakeholder register Stakeholder engagement plan