Question: Linda is managing a multi-national project that utilizes several subproject teams. Before the last team meeting, the sponsor asked her to bring a Control Account
Linda is managing a multi-national project that utilizes several subproject teams. Before the last team meeting, the sponsor asked her to bring a Control Account Plan for him to review. Which of the following statements is MOST correct regarding the Control Account Plan?
A. A control account plan is a node on the WBS that will be used during Risk Monitoring and Control.
B. A control account plan is a node on the WBS used for planning when the work packages cannot currently be defined.
C. A control account plan is a plan of how subcontractor costs will be charged, managed, and controlled.
D. A control account plan should be defined and costs should be controlled at the activity level.