Question: Resources are estimated against which project entity: A. The work packages. B. The schedule activities. C. The elements of scope. D. The level set by
Resources are estimated against which project entity:
A. The work packages.
B. The schedule activities.
C. The elements of scope.
D. The level set by the project office.