Question: 'The activity list should include: A. 'The schedule activities on the project that are on the critical path. B. A subset of all schedule activities.
'The activity list should include:
A. 'The schedule activities on the project that are on the critical path.
B. A subset of all schedule activities.
C. All of the schedule activities defined on the project.
D. A superset of the schedule activities for this and related projects.