Question: The project's business case is an input to the Develop Project Charter process. Organizational process assets are input to the Develop Project Charter process. When

The project's business case is an input to the Develop Project Charter process.

Organizational process assets are input to the Develop Project Charter process.

When projects are executed for external customers, a contract or an agreement is used as an input to the charter.