Question: 1) Steve, the project manager for an ERP implementation project, was asked by the client via a change request to delay the implementation of one
1)Steve, the project manager for an ERP implementation project, was asked by the client via a change request to delay the implementation of one of the modules by one week. What should Steve do first in this situation?
A.Instruct the team member responsible for the module to delay the implementation as per the client's request.
B.Deny the request as it will delay the entire project.
C.Inform the sponsor about the change request.
D.Evaluate the impact of the requested change.
2.Which of the following is not true about the fundamental functionally of the Control Quality process?
A.Implement approved changes to quality.
B.Recommend changes, corrective and preventive actions, and defect repairs to integrated Change Control in order to eliminate noncompliance in the project deliverables.
C.Ensure that the deliverables of the project comply with relevant quality standards.
D.Ensure project work is directed toward the completion of the defined scope.
3) John, the project manager, is in the process of Develop Project Charter to develop a document to formally authorize a project or a phase and identify the business objectives and needs, current understanding of the stakeholders' expectations, and the new product, service, or result that it is intended to satisfy. Which one of the following is not an input to this Develop Project Charter process?
A.Enterprise Environmental Factors
B.Business Documents-Business Case and Benefit Management Plan
C.Agreements
D Project Management Plan
4.During which specific process does the project manager prevent scope changes from overwhelming the project?
A.Define Scope
B.Validate Scope
C.Control Scope
D.Perform Integrated Change Control
5.You are currently working in the Direct and Manage Project Work process to complete the work defined in the project management plan to satisfy the project specifications and
objectives. All of the following are outputs from the Direct and Manage Project Work process except?
A. Deliverables
B.Final products, service, or result transition
C.Change requests
D.Work Performance data